Contents
1. Open the desired view.
2. Click the View tab > Graphics panel > Visibility/Graphics.
3. On the Model Categories tab of the Visibility/Graphics dialog, scroll down to Site, and expand it.
4. Select the following three elements:
5. Click OK.
In the Revit site model, copy and paste the building instance. Adjust the position, both in plan view and in elevation. Now, you have to create a new Shared Site. Click on the Shared Site button in the instance properties of the linked model.17 oct. 2019
When you combine multiple models and files in a single project, use shared coordinates to establish the positions of the files in relation to each other. A Revit project has internal coordinates for all the elements that compose the model in a project.13 juil. 2021
How do I relocate a project in Revit?
1. Click Manage tab Project Location panel Position drop-down (Relocate Project). You use the tool just like the Move tool.
2. Move the project graphically in the view. See Move Elements with the Move Tool.
1. Open the host model whose coordinates you want to reset.
2. Click Manage tab Project Location panel Coordinates drop-down (Reset Shared Coordinates).
3. Click to close the message indicating the shared coordinates have been reset.
What is the difference between overlay and attachment in Revit?
When linking a Revit model, Revit gives two options: Attach or Overlay. This defines the visibility of nested models (models linked to the link) in the main model. Attachment loads nested linked models and displays them in the project, Overlay only loads the linked model (and not the ones linked into it).23 août 2018
Shared parameters are definitions of parameters that you can add to families or projects. Shared parameter definitions are stored in a file independent of any family file or Revit project; this allows you to access the file from different families or projects.7 mai 2020
How do you create a project base point in Revit?
1. Click View tab > Graphics panel > Visibility/Graphics.
2. On the Model Categories tab of the Visibility/Graphics dialog, scroll down to Site.
3. To display the project base point, select Project Base Point.
4. To display the survey point, select Survey Point.
How do you move a project base point in Revit without moving a building?
1. In the site plan view or another view that displays the project base point, select the project base point.
2. Drag the project base point to the desired location.
3. Optional: To ensure that the project base point does not move inadvertently, pin it in place by clicking Modify tab Modify panel (Pin).
How do you move the elevation of a project in Revit?
1. Open an “elevation view” (north, east or any of that, even a section)
2. Go to “Manage”
3. at the “Project Location” on manage click on “Position” tab and choose “Relocate Project”
How do you move a building vertically in Revit?
How do you find Coordinates in Revit?
1. Open the host model.
2. Link the file from which you want to acquire coordinates. The link can be topography, a DWG or DWF file, or a Revit model.
3. Click Manage tab Project Location panel Coordinates drop-down (Acquire Coordinates).
4. Place the cursor on a link, and click.
How do you plot a lot bearing in Revit?
How do you change Coordinates in Revit?
1. Click Annotate tab Dimension panel (Spot Coordinate).
2. In the Type Selector, select the type of spot coordinate to place.
3. On the Options Bar, select or clear Leader.
4. If you want the elevation to display in addition to the spot coordinates, do the following:
5. Select an edge of an element or a point on a toposurface.