Where is my project base point in Revit?

Open the desired view. Click View tab Graphics panel (Visibility/Graphics). On the Model Categories tab of the Visibility/Graphics dialog, scroll down to Site, and expand it. To display the project base point, select Project Base Point.21 jan. 2021

How do you find the base point of a project?

1. Open the desired view.

2. Click View tab Graphics panel (Visibility/Graphics).

3. On the Model Categories tab of the Visibility/Graphics dialog, scroll down to Site, and expand it.

4. To display the project base point, select Project Base Point.

5. To display the survey point, select Survey Point.

How do you set a project base point in Revit?

1. Open the site plan view or another view that displays it.

2. To select the project base point, move the cursor over the symbol and look at the tooltip or the status bar.

3. Drag the project base point to the desired location.

How do you set a project base point and survey point in Revit?

1. Click View tab > Graphics panel > Visibility/Graphics.

2. On the Model Categories tab of the Visibility/Graphics dialog, scroll down to Site.

3. To display the project base point, select Project Base Point.

4. To display the survey point, select Survey Point.

What is project base point in Revit?

The project base point can be used to establish a reference for measuring distances and positioning objects in relation to the model. … When you first create a Revit model, the project base point is located at the internal origin. When starting a project, decide where in the model the project base point will be placed.22 juil. 2021

INTERESTING:   Revit can't print to pdf?

How do you move a project base point in Revit without moving a building?

1. In the site plan view or another view that displays the project base point, select the project base point.

2. Drag the project base point to the desired location.

3. Optional: To ensure that the project base point does not move inadvertently, pin it in place by clicking Modify tab Modify panel (Pin).

How do I reset a project base point in Revit?

1. Select the project base point and unclip it.

2. Right-click the project base point, and click Move to Startup Location.

What is the difference between project base point and survey point?

The project base point defines the origin (0,0,0) of the project coordinate system. Use the project base point as a reference point for measurements across the site. The survey point identifies a real-world location near the model, such as a corner of the project site or the intersection of 2 property lines.7 mai 2020

How do you move project base point more than 10 miles?

1. In 2020.2. 1 and earlier: Un-clip base point and use Relocate Project to move project base point.

2. In 2020.2. 2 and later: Go to Manage > Coordinates > Specify Coordinates at Point.

What is the method to georeference a Revit file?

Revit 2018 now has the option to use the Geo-Referenced data from a CAD file that was used to Acquire Coordinate data. When you link and position a Geo-Referenced CAD file, you use the Acquire Coordinates feature in Revit to share coordinate system data between the Revit and CAD file.12 déc. 2017

INTERESTING:   How to offset in revit?

What is a survey point?

The survey point represents a known point in the physical world, such as a geodetic survey marker. The survey point is used to correctly orient the building geometry in another coordinate system, such as the coordinate system used in a civil engineering application.

How do you change the ground level in Revit?

1. Select the ground level line and specify elevation:

2. Ground level still says 0. Select the ground level line and change the type to Shared Datum:

3. Ground level now shows the Shared Datum levels:

How do you move a project base point in Revit 2020?

1. In the site plan view or another view that displays the project base point, select the project base point.

2. Click the clip to change its state to clipped or unclipped, depending on how you want to move the project base point.

3. Drag the project base point to the desired location.

What is a project point?

A project point cloud presents the project’s scan data in an optimized spatial structure for fast visualization of large amounts of scan points. Scan points are loaded and visualized on demand based on the camera position and point visibility, allowing users to view all scans of a scan project at once.2 juil. 2018

What is survey point Revit?

The survey point provides a real-world context for the Revit model. It represents a known point in the physical world, such as a geodetic survey marker or the intersection of 2 property lines. … In a Revit model, the survey point defines a reference point for the survey coordinate system.21 jan. 2021