Contents
1. Open the model for which you want to bring the proper coordinates into.
2. Turn on the visibility of the site points.
3. Create a new shared site and rename it.
4. Link in the model with the proper shared site reference.
5. Relocate your model.
6. Remove the linked site file.
What is coordinates in Revit?
Revit uses 2 coordinate systems: a survey coordinate system and a project coordinate system. … It uses a selected point within the property boundary or within the extents of the project as a reference for measuring distances and positioning objects in relation to the model.22 juil. 2021
1. Optional: Display the project base point and the survey point in the current view.
2. Click Manage tab Project Location panel Coordinates drop-down (Specify Coordinates at Point).
3. Place the cursor on a reference point of the model.
4. Click the reference.
5. Enter values for the selected reference.
6. Click OK.
Shared parameters are definitions of parameters that you can add to families or projects. Shared parameter definitions are stored in a file independent of any family file or Revit project; this allows you to access the file from different families or projects.7 mai 2020
How do you set a coordinate system in Revit?
Click on the Manage Tab > Coordinates > Specify Coordinates at a Point. Click on the model line at the known origin point. The Specify Shared Coordinate dialog will open. Enter the coordinate values, the correct datum (Elevation) and the angle to True North.
What are the 3 points in Revit?
1. About Positioning.
2. Workflow: Positioning.
3. Project Base Point and Survey Point. About the Project Base Point. About the Survey Point. Display the Project Base Point and the Survey Point. Define the Project Base Point.
4. Location Weather and Site Dialog: Location Tab.
5. Location Weather and Site Dialog: Weather Tab.
How do you set a project location in Revit?
1. Click Manage tab Project Location panel (Location).
2. On the Location tab, for Define Location by, select one of the following:
3. Enter or select the desired location.
4. Optional: For energy analysis, select a nearby weather station from the list.
How do I relocate a project in Revit?
1. Click Manage tab Project Location panel Position drop-down (Relocate Project). You use the tool just like the Move tool.
2. Move the project graphically in the view. See Move Elements with the Move Tool.
1. Open the host model whose coordinates you want to share with the linked model.
2. Click Manage tab Project Location panel Coordinates drop-down (Publish Coordinates).
3. Place the cursor on a linked model instance and click.
4. Select a named position from the linked model, and click OK.
What is the difference between overlay and attachment in Revit?
When linking a Revit model, Revit gives two options: Attach or Overlay. This defines the visibility of nested models (models linked to the link) in the main model. Attachment loads nested linked models and displays them in the project, Overlay only loads the linked model (and not the ones linked into it).23 août 2018
How do you plot a lot bearing in Revit?
When you combine multiple models and files in a single project, use shared coordinates to establish the positions of the files in relation to each other. A Revit project has internal coordinates for all the elements that compose the model in a project.13 juil. 2021
How do you link topography in Revit?
1. Specify coordinates for the building model.
2. Open a plan view or a 3D view for the building model.
3. Click Insert tab Link panel (Link Topography).
4. In the Link Topography dialog, navigate to the topography.
5. Select the desired topography, and click Link.
1. Open the host model whose coordinates you want to reset.
2. Click Manage tab Project Location panel Coordinates drop-down (Reset Shared Coordinates).
3. Click to close the message indicating the shared coordinates have been reset.